DOMINION ENERGY QUESTAR PIPELINE, LLC:    System Wide Notices

Notice Type DescPost Date/TimeNotice Eff Date/TimeNotice End Date/TimeNotice IDSubjectRsp Date/TimeNotice StatPrior NoticeReqrd RspCritical
STORAGE/OFO/PLND OUTAGE09/10/2021 11:21 AM09/20/2021 09:00 AM10/13/2021 06:00 PM301362021 CLAY BASIN INJECTION TEST-1-5Y
1 - 1
All listed times are CCT
Notice Text
Dominion Energy Questar Pipeline has scheduled the Clay Basin Injection test for gas days October 2-13, 2021. Key dates are as follows:

Monday, September 20, 2021: OFO letters indicating injection requirements for gas days October 5 and 6 will be issued to all FSS holders.

Saturday October 2, 2021 to Monday, October 4, 2021: Reservoir conditioning. Field on physical injection only with no withdrawal nominations accepted. However, transfer nominations will be accepted.

Tuesday, October 5, 2021: Based on the OFO requirements, a constant 160 mmcf/d (166 mdth/d) injection rate is required to ensure all wells are open and flowing. No withdrawal nominations accepted, however transfer nominations will be accepted.

Wednesday, October 6, 2021: Based on the OFO requirements, a constant 160 mmcf/d (166 mdth/d) injection rate is required. No withdrawal nominations accepted, however, transfer nominations will be accepted.

Thursday, October 7, 2021 to Wednesday, October 13, 2021: Reservoir shut-in. Only transfer nominations will be accepted.

Thursday, October 14, 2021: Return to normal service. Injection and Withdrawal nominations accepted

Please contact your Marketing and Contracting representative or the Customer Services hotline at 801-324-5200 should you have questions.